The Piling Engineer must do the following:-
1- schedule the production rate with the available machines in the site.
2- check the soil report and follow up the drilling to make sure of the efficiency and accuracy of the foundation work
3- schedule the material manufacturing as per the site requirement
4- monitor the material quantity theoretically and actual
5- issue reports, RFI, IR, and third party test schedules
6- organize the site working teams to reach maximum production with high quality
7- follow up with maintenance teams to keep the equipment in good condition
8- report back and discuss the operation with his seniors to achieve a successful project